Upcoming Roadworks Around Fulham
Traffic delays likely due to lane and road closures in the area
A304 Fulham Road, London, Hammersmith And Fulham |
18 June — 19 June |
|
|
Delays likely Traffic control (two-way signals) |
|
Works location: A304 |
|
|
Works description: This Permit Is For Thames Water, Which Will Involve Carrying Out A New 2x32mm Customer Supply And Connection To The 4" Water Mains, Works In The Footway And Carriageway |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A3219 Munster Road, London, Hammersmith And Fulham |
18 June — 19 June |
|
|
Delays likely Traffic control (two-way signals) |
|
Works location: A3219 |
|
|
Works description: 1x32mm Ne W Water Supply Connection, Footway And In Carriageway. Ourintention Is To Complete The Permanent Reinstatement In The Same Phase |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
B349 Lower Richmond Road, Putney, London, Wandsworth |
18 June — 20 June |
|
|
Delays likely Traffic control (two-way signals) |
|
Works location: B349 |
|
|
Works description: Lay New Service To No. 121 - Excavate In The Nearside Carriageway Maintaining Traffic Flow Using 2 Way Lights As Per Tm Plan, Excavate In The Nearside Footway Maintaining 1.2m For Pedestrians. D+1 Reinstatement Sunday 05/06/2016 - Tm Plan Attached - As Per Site Meeting With Chris Pratt And Scott Richardson |
|
|
Responsibility for works: SGN |
|
|
Current status: Planned work about to start |
|
|
|
|
A3218 Lillie Road, London, Hammersmith And Fulham |
18 June — 18 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: A3218 |
|
|
Works description: Reinstate A Type Pillar Box |
|
|
Responsibility for works: Romec Ltd |
|
|
Current status: Planned work about to start |
|
|
|
|
A3218 Lillie Road, London, Hammersmith And Fulham |
18 June — 21 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: A3218 |
|
|
Works description: Repair Patch- Remedial Reinstatement In The Footway |
|
|
Responsibility for works: Virgin Media |
|
|
Current status: Planned work about to start |
|
|
|
|
A3219 Munster Road, London, Hammersmith And Fulham |
17 June — 21 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: A3219 |
|
|
Works description: Service Pipe Reconnect In Footway. Our Intention Is To Complete Thepermanent Reinstatement In The Same Phase |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A3219 Munster Road, London, Hammersmith And Fulham |
18 June — 19 June |
|
|
Delays possible Traffic control (priority working) |
|
Works location: A3219 |
|
|
Works description: Install 14m Of 1 Way Poly Duct In Footway,Install 8m Of 1 Way Poly Duct In Carriageway |
|
|
Responsibility for works: BT |
|
|
Current status: Planned work about to start |
|
|
|
|
Finborough Road, London, Kensington And Chelsea |
17 June — 18 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
|
|
Tadema Road, London, Kensington And Chelsea |
17 June — 18 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
|
|
Tadema Road, London, Kensington And Chelsea |
18 June — 18 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Virgin Media |
|
|
Current status: Planned work about to start |
|
|
|
Information supplied by roadworks.org
|