A217 Wandsworth Bridge Road, London, Hammersmith And Fulham |
26 April — 04 May |
|
|
Delays likely Lane closure |
|
Works location: A217 |
|
|
Works description: Network Operations Faults:Install / Replace Link Box: (Approx Depth 450mm):Lb No. 130910 - Replace A Very Poor Condition Link Box In The Footway. Part Of Hse Initiative To Replace All Identified High Risk Link Boxes. Until The Excavation On The Link Box Is Complete We Are Not Certain On What Obstacles We May Find. |
|
|
Responsibility for works: UK Power Networks |
|
|
Current status: Planned work about to start |
|
|
|
|
A219 Fulham Palace Road, London, Hammersmith And Fulham |
25 April — 04 May |
|
|
Delays likely Traffic control (multi-way signals) |
|
Works location: A219 |
|
|
Works description: Build 2 Concrete Chamber 915mm X 445mm X 965mm Deep In Footway,Install 115m Of 1 Way Poly Duct In Footway,Install 25m Of 1 Way Poly Duct In Carriageway |
|
|
Responsibility for works: BT |
|
|
Current status: Planned work about to start |
|
|
|
|
A308 New King's Road, London, Hammersmith And Fulham |
25 April — 25 April |
|
|
Delays likely Traffic control (multi-way signals) |
|
Works location: A308 |
|
|
Works description: 11/023 Tel56988 - Repair Damaged Traffic Signal Detection By Slotcutting Sd1 Loop, 2100 - 2359, Ne/B Lane 1 Closed Only |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
|
|
A308 New King's Road, London, Hammersmith And Fulham |
25 April — 25 April |
|
|
Delays likely Lane closure |
|
Works location: A308 |
|
|
Works description: "Set Up Of Tm To Replace Lamps On Traffic Signal Pole 11 Short Stay." Lane 1 Closed Ne/B Only |
|
|
Responsibility for works: Transport For London |
|
|
Current status: Planned work about to start |
|
|
|
|
A308 New King's Road, London, Hammersmith And Fulham |
25 April — 27 April |
|
|
Delays likely Traffic control (Stop/Go boards) |
|
Works location: A308 |
|
|
Works description: W.R.P. - Upgrade Of 3 Bay Non Ad Bus Shelter, Back Of Path, For And On Behalf Of Transport For London 0113/0218 2458444 |
|
|
Responsibility for works: London Transport |
|
|
Current status: Planned work about to start |
|
|
|
|
A308 New King's Road, London, Hammersmith And Fulham |
26 April — 28 April |
|
|
Delays likely Road closure |
|
Works location: A308 |
|
|
Works description: Laying Anti Skid To The Crossing Points |
|
|
Responsibility for works: Hammersmith and Fulham London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
|
A308 New King's Road, London, Hammersmith And Fulham |
26 April — 28 April |
|
|
Delays likely Road closure |
|
Works location: A308 |
|
|
Works description: Laying Anti-Skid To The Crossing Point |
|
|
Responsibility for works: Hammersmith and Fulham London Borough Council |
|
|
Current status: Planned work about to start |
|
|
|
|
A3217 King's Road, London, Kensington And Chelsea |
25 April — 29 April |
|
|
Delays likely Lane closure |
|
Works location: A3217 |
|
|
Works description: Connections Highway Services:New Individual Supply::New Electricity Supply To Bt Cabinet Joint Hole In Footway Lane Closure Temp Walkway In Carriageway Bus Stop Suspension Tm Plan |
|
|
Responsibility for works: UK Power Networks |
|
|
Current status: Planned work about to start |
|
|
|
|
A3219 Dawes Road, London, Hammersmith And Fulham |
26 April — 04 May |
|
|
Delays likely Lane closure |
|
Works location: A3219 |
|
|
Works description: Network Operations Faults:Install / Replace Link Box: (Approx Depth 450mm):Replace A Very Poor Condition Link Box In The Footway. Part Of Hse Initiative To Replace All Identified High Risk Link Boxes. Until The Excavation On The Link Box Is Complete We Are Not Certain On What Obstacles We May Find. |
|
|
Responsibility for works: UK Power Networks |
|
|
Current status: Planned work about to start |
|
|
|
|
|
|
Townmead Road, London, Hammersmith And Fulham |
25 April — 26 April |
|
|
Delays likely Traffic control (two-way signals) |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|